The Fountain Pen, Guelph's On-Line News
ADV: Chris Bradley Landscape

Construction Notice: Hadati Road Paving

Web posted on June 12, 2017

Working with Capital Paving Inc, the City will be paving Hadati Road from Cassino Avenue to Auden Road.

The project will: Remove and repair concrete curbs, Raise manholes, and Repave the road surface. All work will take place on City property.

Road work begins June 15

Road work is expected to start on or about June 15 and continue for approximately three weeks, weather permitting.

Construction impacts
There will be a lane reduction but two-way traffic will be maintained for the duration of the work.

Some noise due to equipment movement may be expected during work hours (Monday to Friday, 7 a.m. to 7 p.m.). The contractor will make every effort to minimize noise.

Property access and parking
Every effort will be made to maintain access to driveways within the work area during working hours (Monday to Friday, 7 a.m. to 7 p.m.). Construction activities and equipment movement may temporarily impact access to private property and delays should be expected. All driveway access will be restored at the end of each work day.

On-street parking will not be permitted on Hadati Road during the construction period.

Pedestrian access - Pedestrian sidewalk access will be maintained.

City services
There will be no interruption to any City services during construction. Waste collection will not be affected. Please continue to place your green, blue and grey carts at the curb, as per your regular schedule.

The City appreciates your patience, understanding and co-operation during this important construction project. Any updates will be posted under Annual asphalt at guelph.ca/construction.


Back