Update - Wellington Street Water Main Construction

Web posted on September 16, 2014

Guelph, ON, September 15, 2014 - Earlier this month, crews unearthed eight drums filled with industrial solvents during construction of the Paisley-Clythe feedermain near the Wellington Street/Hanlon Expressway interchange. The City halted the work, removed the liquid and is working with the Ontario Ministry of the Environment and Climate Change (MOECC) to determine next steps before removing any remaining contaminated materials.

"Knowing the history of industrial and landfill activity in the area, we did several scans and tests before construction. Before work continues, we'll conduct more detailed scans to gather more specific information so we can take further precautions if necessary," said Kealy Dedman, City Engineer. Next steps

The City, its consultant MMM Group, and the MOECC developed the following plan to be implemented over the coming weeks; before crews continue installing the watermain.

--> Prepare an updated health and safety plan before continuing intrusive (digging) work

--> Perform geophysical and electromagnetic surveys of the area and report findings to the MOECC and Wellington-Dufferin-Guelph Public Health (WDGPH)

--> Following the results of the geophysical survey, the appropriate next steps will be determined and carried out following approval of the plan by MOECC

About The Project
The Paisley-Clythe Drinking Water Feedermain is a new watermain required to increase the reliability of the supply between the City's F.M. Woods Reservoir and Pumping Station and the Paisley and Clythe Reservoirs at the west and east ends of the City.

Construction began in March 2014 and is expected to be completed in March 2015, weather permitting. Construction within the City parks along the route will generally be restricted to the winter months, in order to avoid impacting the playing fields.